Leschenault Leisure Centre Courts Expansion

Promoting participation, performance and integrity in the sport and recreation industry to support a healthy lifestyle for all people.

The Leschenault Leisure Centre (LLC) is the premier sporting and aquatic centre in the Shire of Harvey and a leading South West sporting facility.

The LLC Expansion project will allow the centre to maintain this position and provide crucial sporting facilities for one of Western Australia’s fastest growing communities.

Project Update June 2026

The LLC Court Expansion project has re-commenced with a review of the final design and value engineering process. While we are awaiting the signing of the funding provided by the election commitment, there are activities occurring in the background.

Shire staff have attended stakeholder sessions with both the Leschenault Netball Association and the Australind Basketball Association to reaffirm their top priorities in the court expansion project, and to communicate re-scoping of the project that is required to meet the constraints of funding availability and rising construction costs.

The Shire is committed to delivering a resilient, community-focused facility through strong collaboration with stakeholders ensuring responsible investment of public funds while prioritising functionality, safety, sustainability, and long-term value for the Shire of Harvey community.

The project is scheduled to commence construction in late 2026.

Background

The LLC indoor courts, specifically Courts 3 and 4, were constructed in 2000 and are now showing clear signs of age and deterioration. The playing surfaces are damaged, and the building structure has degraded over time. Additionally, poor ventilation within the hall creates excessive heat and condensation, resulting in potentially unsafe and slippery playing conditions.

The Shire has completed an extensive consultation process, needs and feasibility studies and developed concept plans and is working closely with users of the facility to refine the design.

There is extensive support from a number of State Sporting Associations to hold regional competitions and significant sporting events, and an immediate and urgent demand from community and clubs for places to play.

Project feasibility

This project is part of the WA Government’s PlayOn WA, an exciting initiative to deliver 2,030 community infrastructure items across WA by 2030.

Secured funding contributions currently total $23,500,000, as outlined below:

  • State Government (Planning and Design): $3,000,000
  • State Government (Construction Contribution): $15,500,000
  • Shire of Harvey: $5,000,000

To align the project scope with the available funding, targeted cost reductions will be achieved through value engineering, scope refinement, and prioritisation of essential project components.

The project governance structure for this project includes:

  • Shire Council and Executive Leadership Team
  • Project Management team
  • Project Control Group
  • Sport and Recreation Advisory Group
  • Local Emergency Management Committee

Project Timeline

Completed
September 2019
Council endorsed the Leschenault Recreation Park Master Plan.
Completed
April 2021
Council endorsed the Concept and Feasibility of the LLC Court Expansion and supported the ongoing development of the project.
Completed
October 2021-March 2022
Operating Feasibility Study, Management Plan and Business Case
Completed
November 2021
Council appointed Hodge Collard Preston as the Architectural Firm to design the new courts.
Completed
December 2021
LLC Expansion Project launched with start-up meeting held on site.
Completed
December 2021-May 2022
Design Documentation.
Completed
January-June 2022
Community consultation opportunities
Completed
June 2022
Final design completed and presented to Council, ready for tender
Completed
April 2023
Council endorsed design and staging options and identified project as shovel ready.
Completed
June 2025
Labor government election commitment announcement
Completed
March 2026
Draft Financial Assistance Agreement agreed to by all parties, and in preparation for signing
Completed
May 2026
Key Stakeholder priorities sessions
In progress
June 2026
Value Engineering on Stage 1B stage, update of detailed design documentation
In progress
July 2026
Preparation of Tender documentation and statutory approvals
In progress
August 2026
Procurement Phase
In progress
November 2026
Project Commencement
In progress
September 2028
Project Completion